10 Knowledge Areas × 5 Process Groups · Click any process to study · Mark as Studied · Auto-saves your progress & notes
| Knowledge Area ↓ / Process Group → | Initiating | Planning | Executing | Monitoring & Controlling | Closing |
|---|---|---|---|---|---|
| TOTAL = 49 | 2 | 24 | 10 | 12 | 1 |
| Process Group | Count | Memory Trick |
|---|---|---|
| Initiating | 2 | Charter + Stakeholders |
| Planning | 24 | Largest — "plans for everything" |
| Executing | 10 | "Do the work" verbs (Direct, Manage, Acquire, Develop, Conduct, Implement) |
| Monitoring & Controlling | 12 | "Control / Monitor / Validate" verbs |
| Closing | 1 | Just Close Project or Phase |
| KA | # | KA | # |
|---|---|---|---|
| Integration | 7 | Resource | 6 |
| Scope | 6 | Communications | 3 |
| Schedule | 6 | Risk | 7 |
| Cost | 4 | Procurement | 3 |
| Quality | 3 | Stakeholder | 4 |
| Formula | What it tells you |
|---|---|
| EV = % complete × BAC | Earned Value |
| CV = EV − AC | Cost Variance (negative = over budget) |
| SV = EV − PV | Schedule Variance (negative = behind) |
| CPI = EV / AC | <1 = over budget |
| SPI = EV / PV | <1 = behind schedule |
| EAC = BAC / CPI | Forecast at completion (typical case) |
| ETC = EAC − AC | Estimate to complete |
| VAC = BAC − EAC | Variance at completion |
| TCPI = (BAC − EV) / (BAC − AC) | To-Complete Performance Index |
| PERT = (P + 4M + O) / 6 | Beta/Three-point estimate |
| SD = (P − O) / 6 | Standard deviation of estimate |
| Communication channels = n(n−1)/2 | n = number of stakeholders |
| EMV = Probability × Impact | Expected Monetary Value |