PMP 49 Process Table — PMBOK 6 (with PMBOK 7 notes)

10 Knowledge Areas × 5 Process Groups · Click any process to study · Mark as Studied · Auto-saves your progress & notes

Progress: 0 / 49 (0%)
Initiating (2)
Planning (24)
Executing (10)
Monitoring & Controlling (12)
Closing (1)
Studied (your progress)
Knowledge Area ↓ / Process Group → Initiating Planning Executing Monitoring & Controlling Closing
TOTAL = 49 22410121

📋 Master Cheat Sheet — Memorize Before Exam Day

Process Group totals (these MUST be instant recall)

Process GroupCountMemory Trick
Initiating2Charter + Stakeholders
Planning24Largest — "plans for everything"
Executing10"Do the work" verbs (Direct, Manage, Acquire, Develop, Conduct, Implement)
Monitoring & Controlling12"Control / Monitor / Validate" verbs
Closing1Just Close Project or Phase

Knowledge Area totals (memorize these counts too)

KA#KA#
Integration7Resource6
Scope6Communications3
Schedule6Risk7
Cost4Procurement3
Quality3Stakeholder4

The 4 "lonely" processes (no siblings in their Process Group within their KA)

Universal exam tactics (work on ANY situational question)

Formulas you MUST memorize (Cost / EVM)

FormulaWhat it tells you
EV = % complete × BACEarned Value
CV = EV − ACCost Variance (negative = over budget)
SV = EV − PVSchedule Variance (negative = behind)
CPI = EV / AC<1 = over budget
SPI = EV / PV<1 = behind schedule
EAC = BAC / CPIForecast at completion (typical case)
ETC = EAC − ACEstimate to complete
VAC = BAC − EACVariance at completion
TCPI = (BAC − EV) / (BAC − AC)To-Complete Performance Index
PERT = (P + 4M + O) / 6Beta/Three-point estimate
SD = (P − O) / 6Standard deviation of estimate
Communication channels = n(n−1)/2n = number of stakeholders
EMV = Probability × ImpactExpected Monetary Value